After some tense moments between my concrete guys, LA Foundations, and the Weld County Building Inspector, he gave us the go ahead to pour the concrete. It seems they couldn't quit agree as to the proper way to suspend the #4 rebar in the concrete--the inspector didn't like it tied to nails and perpendicular supports, however, Alonzo assured him this has been his common practice for 15 plus years. After working it all out (1 hour later), the actual pour went very smoothly and we'll be forming up walls tomorrow and Friday with the hopes of pouring them next Monday.