In the past week, we have worked on finishing up running the water line, installing perimeter drain, and damproofing and insulating the exterior foundation walls. Attached are the pics that show these processes. On the docket for this week: Our electric lateral line will be run from the transformer; we'll then set the temp. power pedestal. All of the underground plumbing, electric, insulation for slab, wire mesh, and radiant tubing should be run this week! It'll be a big week for all the trades involved and baring any setbacks, we should be pouring the slab early next week and be framing by the middle of next week--hopefully!